VTA’s BART Silicon Valley Phase II Extension Project – End of Year 2025 Newsletter

end of year newsletter

https://youtube.com/shorts/IECfUYXMuQ8?si=cann2EcM5ywQxNEF Key Milestones Achieved on BSVII Project  The BART Silicon Valley Phase II (BSVII) project has reached a number of major milestones, from major construction progress to critical funding updates. As we wrap up fall and head into the end of the year, we’re excited to share the latest updates and developments that continue to move the project […]

VTA’s BART Silicon Valley Phase II Extension Project – Summer 2025

summer 2025 newsletter

BSVII Project Update    The BART Silicon Valley Phase II (BSVII) project is making steady progress after achieving a significant milestone in late 2024 with the Federal Transit Administration (FTA) accepting the project into the final phase of the federal funding process known as New Starts Engineering. The FTA has committed $5.1 billion to the project, […]

BART Silicon Valley Phase II Extension Project Monthly Construction Update – August 2025

August Construction Newsletter

VTA’s BART Silicon Valley Phase II (BSVII) Project continues to progress construction activities at the West Portal at Newhall Yard & Maintenance Facility. Activities are within VTA property between Brokaw Road, Newhall Drive, Coleman Avenue, and the railroad tracks. Continued Work in May – What to Expect: Current work activities at West Portal will occur […]

Behind the Scenes at the BART Silicon Valley Phase II West Portal Construction Site

image of media tour of West Portal construction site

On Monday, June 23, 2025, the Santa Clara Valley Transportation Authority (VTA) welcomed local media for an exclusive behind-the-scenes look at the BART Silicon Valley Phase II Project. The focus was the West Portal construction site—the future launch point for the tunnel boring machine that will help bring BART service into the heart of San […]