BART Silicon Valley Phase II Extension Project Monthly Construction Update – March 2026

VTA’s BART Silicon Valley Phase II (BSVII) Project continues to progress construction activities at the West Portal at Newhall Yard & Maintenance Facility. Activities are within VTA property between Brokaw Road, Newhall Drive, Coleman Avenue, and the railroad tracks. Continued Work in May – What to Expect: Current work activities at West Portal will occur […]

BART Silicon Valley Phase II Extension Project Monthly Construction Update – February 2026

VTA’s BART Silicon Valley Phase II (BSVII) Project continues to progress construction activities at the West Portal at Newhall Yard & Maintenance Facility. Activities are within VTA property between Brokaw Road, Newhall Drive, Coleman Avenue, and the railroad tracks. Continued Work in May – What to Expect: Current work activities at West Portal will occur […]

BART Silicon Valley Phase II Extension Project Monthly Construction Update – January 2026

VTA’s BART Silicon Valley Phase II (BSVII) Project continues to progress construction activities at the West Portal at Newhall Yard & Maintenance Facility. Activities are within VTA property between Brokaw Road, Newhall Drive, Coleman Avenue, and the railroad tracks. Continued Work in May – What to Expect: Current work activities at West Portal will occur […]

BART Silicon Valley Phase II Extension Project Monthly Construction Update – December 2025

December Construction Newsletter

VTA’s BART Silicon Valley Phase II (BSVII) Project continues to progress construction activities at the West Portal at Newhall Yard & Maintenance Facility. Activities are within VTA property between Brokaw Road, Newhall Drive, Coleman Avenue, and the railroad tracks. Continued Work in May – What to Expect: Current work activities at West Portal will occur […]

BART Silicon Valley Phase II Extension Project Monthly Construction Update – November 2025

November Construction Newsletter

VTA’s BART Silicon Valley Phase II (BSVII) Project continues to progress construction activities at the West Portal at Newhall Yard & Maintenance Facility. Activities are within VTA property between Brokaw Road, Newhall Drive, Coleman Avenue, and the railroad tracks. Continued Work in May – What to Expect: Current work activities at West Portal will occur […]

BART Silicon Valley Phase II Extension Project Monthly Construction Update – October 2025

October Construction Newsletter

VTA’s BART Silicon Valley Phase II (BSVII) Project continues to progress construction activities at the West Portal at Newhall Yard & Maintenance Facility. Activities are within VTA property between Brokaw Road, Newhall Drive, Coleman Avenue, and the railroad tracks. Continued Work in May – What to Expect: Current work activities at West Portal will occur […]